Manage Tasks in a Round Plan
Learn how to copy tasks to different locations or assets in a Round Plan and perform other task actions like cut, paste, and copy below.
Copy to All Locations and Assets
- Right-click on the task.
- Select Copy to.
- Choose All Locations / Assets.
- Click Continue to Copy to copy the task to all locations present in Route Plan view.
Copy to Custom Locations & Assets
- Right-click on the task.
- Select Copy to.
- Choose Custom Locations / Assets.
- In the Select Locations / Assets to Copy window, select desired locations and assets.
- Click Done.
- Click Continue to Copy to copy the task to selected locations and assets.
Other Task Actions
- Cut Task: Right-click on the task > select Cut.
- Paste Task: Right-click on the task > select Paste.
- Copy Task Below: Right-click on the task > select Copy Below to copy the task directly below the current task.