Reschedule Work
Update planned dates when the current schedule can no longer be met.
Reschedule work when materials, permits, equipment access, production conditions, or technician availability prevent the job from starting or finishing as planned.
- Open the work order from Scheduled Work Orders at Risk or the work-order list.
- Tap Action, then select Reschedule.
- Review the current planned start and end dates.
- Enter the revised dates and times.
- Confirm that the new dates remain within any applicable permit validity and maintenance-plan constraints.
- Save or confirm the revised schedule.
The work order displays the revised planned dates.
Note:
Review the technician assignment, permit validity, and component readiness after rescheduling.
Next: Return to the Dashboard and verify that the risk or blocker is resolved.