Approve or Revert JHA

Once all assigned team members complete field validation and Work Acknowledgement, the JHA moves to the Approve stage.

To approve or revert a JHA:

  1. Navigate to EHSJHA from the left navigation panel.
  2. Go to the Pending Approval tab and select the JHA that needs to be reviewed.
  3. In this stage, the approver can perform the following actions:
    1. Approve – Approve the JHA if all hazards, control measures, and risk assessments are reviewed and acceptable.
    2. Reject – Reject the JHA if it is not valid or no longer required.
    3. Revert – Revert the JHA to the requester if any changes or additional information are required.
    Figure 1. Approve JHA


    The JHA is approved, and now the linked permit can proceed to the next stage.